Sector
Commercial & Retail, NHS
Location
London
The Project
As part of an NHS Trust's wider estate transformation programme, the refurbishment and fit-out of four floors at Capital House, London, was designed to bring more than 250 staff from nine separate locations into a modern, flexible workplace supporting collaboration, efficiency and future growth. The relocation formed part of the Trust's decant phase, freeing the vacated buildings for further works. RAM was appointed to provide project management and contract administration services for the Capital House project.
The scheme involved the reconfiguration of Levels 5, 7, 9 and 15 to accommodate approximately 30 teams, delivering 223 workstations and 12 privacy booths while ensuring business continuity throughout the relocation process. As part of the works all non-compliant distribution boards were replaced to ensure compliance with current regulations and meet project requirements, after being tested signed off and certification issued.
The Challenges
The project was required to support a major reorganisation of the Trust's estate, with staff relocating from sites across St Mary's, Charing Cross and Hammersmith hospitals.
- A Tight Timescale – Design started in May, and the Trust wanted teams moving in from early October. Fitting out the floors one at a time would have taken around six months on site.
- Working Around People – The first teams would move into completed floors while work carried on elsewhere in the building, so every noisy task, delivery and shutdown had to be planned and agreed in advance.
- Strict Site Controls – Every contractor needed to sign in with concierge every day they were note. Lifts, stairs and escape routes had to stay clear at all times as these remained in use for the other users to the building.
- A Fire Alarm System that had to Keep Working – With the increased occupation of the building, the fire alarm had to be maintained across all the floors and required works completed out of hours to minimise disturbance to other building users.
- Confidential Conversations – The new meeting rooms and privacy booths needed genuine speech privacy within open-plan floors.
- Everything Ready at Once – Building works, M&E, ICT, telephony, furniture and office pods all had to come together before each team could move. With eight or more parties involved, one late delivery could hold up a team move.
The Trust needed to maintain its public services throughout the refurbishment and relocation. RAM's role was to coordinate delivery around those operational requirements, with the aim of keeping downtime to a minimum or avoiding it altogether.
The Solution
- Compressed the Programme – We coordinated the technical design from late May and issued the final tender package in late August. In between the tender and issue and returns, the works had been phased to allow for initial enabling works followed by the main works on approval of costs. Returns were due on 1st September, to which works started on site as planned in September. All four floors then started together, each a six-week package staggered a week apart. To allow for a seamless delivery we started works on the 15th floor and worked our way down to the 9th, 7th and finishing up on the 5th floor.
- Dealt with Services Risks Early – We commissioned a fire alarm investigation across all four floors, covering loop capacity, device age and the alterations needed, before the layouts were finalised. We also flagged early that Levels 7 and 15 needed replacement distribution boards and coordinated that design change between the M&E designer, the Trust and CBRE.
- Built Acoustics into the Process – A pre-works survey, specialist advice fed into the design, and post-works testing to verify the meeting rooms and privacy booths.
- Planned Around the Move Programme – We sequenced the floors from Level 15 first to Level 5 last, matching the Trust’s phased team moves, and worked with Trust IT so each floor was ready for its incoming team. We also worked with the furniture installers at the same time to ensure all work stations were ready for staff.
- Tracked Completion Floor by Floor – We logged every outstanding item on each floor (doors, power and data, evacuation equipment, office pods), secured commitments from each party and re-inspected to confirm close-out and issued a snagging list to the contractor.
- Protected the Trust’s Operations – The tender specification set clear rules on working hours, noise, dust, security, DBS checks and escape routes, so contractors priced and planned for a live building from day one.
The Results
The first teams successfully occupied Capital House in 7th October with fully operational ICT systems and no reported issues. Through the concurrent delivery of all four floor fit-outs, RAM helped reduce the construction programme from an estimated 24 weeks to approximately 10 weeks, enabling the Trust to accelerate its relocation strategy with all times fully functional by 14th October.
The completed workspace successfully brought together around 30 teams from nine separate locations, creating a modern and flexible working environment that supports improved collaboration and operational efficiency. The successful completion of the project also enabled the next phase of the Trust's estate transformation programme, including the planned refurbishment of West Acrow, to proceed as scheduled.
Services used:
Project Management
Project Management
RAM provided project management services to coordinate the design, delivery and stakeholder engagement for the four-floor refurbishment, ensuring the project was completed on programme with minimal disruption to other operations.
Project Management
Contract Administration
Contract Administration
RAM provided contract administration services throughout the project, overseeing contract compliance, managing change control, administering project documentation and monitoring progress to support the successful delivery of the works.
Contract Administration
Specification Writing
Specification Writing
RAM provided specification writing services to develop a clear and comprehensive scope of works, defining the project requirements, quality standards and delivery expectations for the successful refurbishment of all four floors.