Bowmer & Kirkland
Sector
The Project
RAM Building Consultancy was tasked with performing an integrity test on the roof, including the syphonic outlets and upstands, to ensure the building was watertight before being handed over to the occupier.
The Challenges
The key objective was to confirm there were no leaks, ensuring the building's roof met the required standards for water integrity, preventing any future issues for the new occupiers.
The Solution
Our team conducted a thorough flow test on the main roof and syphonic outlets over several days, replicating various weather conditions to ensure comprehensive testing.
The Results
The rigorous testing revealed no leaks, and the roof successfully passed the integrity test, allowing the building to be handed over with full confidence in its structural soundness.
Services used:
The Dynamic Leak Investigation service was essential in this project, as it provided a non-invasive method to test for leaks under real-life conditions. By simulating water flow, our team ensured the roof and outlets were thoroughly tested for potential leaks, helping to guarantee the building’s long-term integrity. This method allowed us to quickly identify any vulnerabilities in the roofing system without causing any damage, ensuring the client could move forward with confidence.
Dynamic Leak Investigation